This guide provides owners, designers, specifiers, contractors, and manufacturers with the tools needed to select and specify the methods for concrete repair surfaces prior to the application of a protective system or repair material. Surface preparation is the process by which a sound, clean, and suitably roughened surface is produced on a concrete substrate. Surface preparation includes the removal of laitance, dirt, oil, films, paint, coatings, sound and unsound concrete, and other materials that will interfere with the adhesion or penetration of a sealer, coating, polymer overlay, or repair material. Proper surface preparation will open the pore structure of the concrete substrate and establish profiles suitable for the application of the specified protective system or repair material.
Proper surface preparation is a key element in determining the success of a concrete restoration project. Improper surface preparation may lead to the failure of the protective system or repair material, resulting in further repairs, added expense, and loss of use, and may ultimately compromise the integrity of the structure. The existing conditions of the concrete and the type of protective system or repair material to be applied should be considered in determining the surface preparation method(s). The designer, specifier, contractor, and manufacturer should all participate in the selection of the surface preparation method(s). Detailed attention to proper surface preparation will help ensure the long-term success of the restoration project.
The following tools are contained within the guideline to assist the user in the selection and/ or specification of the proper surface preparation method(s):
Project Evaluation
Concrete surface conditions, material requirements, and job-site conditions will vary considerably for each project. Most projects will have unique conditions and requirements that must be evaluated to determine which surface preparation method(s) is/are suitable for the project and which will ensure the long-term success of the protective system and/or repair material. More than one method may be capable of producing the desired results. Appendix A provides a more complete list of items to be considered and can be used as a checklist in evaluating a project. The checklist will help ensure that the various conditions affecting the surface preparation have been considered.
Substrate condition
The condition of the substrate, including the presence of unsound concrete, bond-inhibiting materials, substrate deterioration, cracking, and surface contaminants, need to be evaluated to determine the nature and degree of preparation required. The surface preparation method must provide a clean, sound substrate with a surface profile appropriate for the specific material installation.
Material requirements
Surface preparation requirements may vary with the material selected. The manufacturer of the system may have specific requirements for surface preparation, including the surface profile and moisture sensitivity, and should be consulted. Proper surface preparation could impact the manufacturer’s warranty. The properties and application requirements of the selected protective system or repair material must be determined prior to the selection of a surface preparation method.
Job-site requirements
Noise, vibration, dust, and water may be generated by various preparation methods. The need for uninterrupted use of the structure, concerns about the operating environment, or the potential for property damage may limit the choices. Mechanical ventilation, available power sources, the size of door openings, and minimum clearance may also affect surface preparation decisions. The surface preparation may also release hazardous contaminants (for example, asbestos from old flooring mastic). Any condition that may affect the method of surface preparation should be considered.
Evaluate Surface Preparation Method(s)
Selecting the method(s) that will provide a clean, sound substrate and optimize the success of the material installation requires knowledge of the available options. The surface profile achieved following the surface preparation is often the primary requirement in specifying the preparation method(s). The method selector chart may be used to make a preliminary identification of the methods capable of producing the required CSP.
Each of the methods capable of meeting the CSP requirement can be compared in the method summaries section, which provides data on the capabilities, limitations, operating requirements, and environmental considerations for each surface preparation method.
Select and Specify Surface Preparation Method(s)
The final selection is based on the relationship between substrate conditions, material requirements, and job-site conditions. The specification may include a CSP range as well as other criteria, such as bond strength. These requirements should be clearly defined in the specification, along with the test method(s) that will be used to evaluate the completed surface preparation. The test procedures described in Appendix B may be used in preparing the specifications to ensure that the desired results are achieved.
Quality Control
The CSP chips (CSP 1-10) provide benchmark profiles to aid in achieving the desired result. The prepared surface should be compared to the CSP chips specified for the project. Tests, such as the tensile bond test, may be performed to verify that all deteriorated or damaged concrete has been removed. Other specified tests should be performed prior to installing the protective system or repair material. The cost of providing additional surface preparation will be significantly less than the cost of correcting a failure of the installed system or repair. Appendix B describes various tests that may be used to evaluate the prepared concrete surface. SSPC-SP 13/NACE No. 6, ASTM D5295, ASTM E1857, and ASTM F2471 provide additional considerations for surface preparation and quality control.
Introduction
In addition to project-specific requirements, the selection of a surface preparation method should ensure that:
This section describes the mechanics used by the various surface preparation methods to remove deteriorated concrete and contaminates from the surface. This information will help users determine the potential of each preparation method to achieve the desired results and also assess the potential for damage to the substrate that may be caused by the individual methods.
Cleaning
Cleaning does not noticeably alter the profile of concrete surfaces. Cleaning and detergent scrubbing are accomplished through one or a combination of the following: the surfactant effect of detergents, the solvent effect of water, the shearing force of brushes, and the force of lowvelocity water. Applicable methods: low-pressure water cleaning and detergent scrubbing.
Acid Etching and Surface Retarder
Acid etching chemically dissolves calcium hydroxide and calcium silicate, which make up the hydrated solids in cement paste. The dissolution of these materials at the surface causes a slight loss of cement paste and produces a very light profile on the exposed surface. Surface retarders slow the hydration of cement, allowing low-pressure water cleaning to remove the retarded layer, creating an exposed aggregate surface. Applicable methods: acid etching and surface retarders.
Abrasion
Abrasive force applied through grinding with stones, abrasive discs, or blocks with embedded diamonds wears away the cement paste, fines, and coarse aggregate at a uniform rate to produce a nearly flat surface having little or no profile (Fig. 4.1). Applicable methods: grinding.
High-Pressure Water Erosion
Erosion causes the flushing away or progressive disintegration of concrete surfaces. A stream of water projected onto the surface under high pressure will result in the gradual erosion of the surface. The impact of the water and the water velocity combine to wear away the cement paste. As exposure to water jetting increases, so will the profile as the softer paste and embedded fines erode, leaving behind “islands” of the harder coarse aggregate. Under prolonged exposure to water jetting, the coarse aggregate will be undercut and washed away (Fig. 4.2). Applicable methods: high- and ultra-high-pressure water jetting.
Impact
Several preparation methods strike the surface repeatedly with hardened points to produce momentary mechanical loads that exceed the strength of the concrete, causing it to fracture. The force of the impact pulverizes and fractures the cement paste and aggregate at and adjacent to the point of contact (Fig. 4.3 and 4.4). Some of the cracks and loosened aggregate may remain, leaving a “bruised” layer at the surface. Applicable methods: scarifying, scabbling, rotomilling, needle scaling, and handheld concrete breakers.
Pulverization
The cutting effect is derived from the collision of small particles traveling at a high velocity against the concrete surface (Fig. 4.5). Because the mass of the particles is comparatively small, their impact is not known to produce bruising. Hard, sharp-edged media and high pressure can produce fast cutting rates. As with water jetting, the cement paste is usually reduced at a faster rate than the coarse aggregate. This difference in removal rate has the effect of exposing and under cutting the coarse aggregate to produce a surface that will become highly profiled as exposure time is increased. Applicable methods: steel shotblasting and abrasive blasting.
Effect on Bond Strength
Several of the preparation methods described may locally damage the prepared substrate. Field studies have shown that bond strengths of surfaces prepared using high-impact mechanical methods are frequently lower compared to surfaces prepared using nonimpact methods. This reduction in bond strength is caused by the fracturing of the cement paste and loosening of the aggregate without fully separating from the surface. This creates a weakened or “bruised” surface layer of interconnecting microcracks typically extending to a depth of 1/8 to 3/8 in. (3 to 10 mm). Microscopic examination usually indicates that cracks initiate at the surface at approximately a 45-degree angle and propagate horizontally to produce a weakened plane (Fig. 5.1a to 5.1c). It is generally accepted that the extent of the damage increases with the weight and power of the equipment used. However, the use of sharp, fine-toothed cutters contacting the surface at a shallow angle may reduce or prevent the development of bruising. The relative risk of introducing bruising or microcracking into the substrate is indicated for each method in Section 5.2. Surfaces prepared using impact methods should be tested using a tensile pulloff test to confirm that the prepared surface does not contain microcracks that may compromise the installation of a repair material or protective system (refer to Appendix B).
Risk of Introducing Microcracking
Figure 5.2 identifies the potential risk of introducing microcracking when performing surface preparation using the method listed.
Surface preparation using methods resulting in a high probability of microcracking, including handheld concrete breakers, rotomilling, and scabbling, generally require further surface preparation to remove the microcracks. Surface preparation using methods resulting in a moderate probability of microcracks, including needle scaling and scarifiers, may require further surface preparation, and the surface should be evaluated to determine if the preparation created microcracks. All surfaces should be tested, regardless of preparation method, to ensure adequate concrete strength and a properly prepared surface (refer to Appendix B).
Several of the methods summarized are capable of producing a range of profiles on concrete surfaces. Communication of project objectives and requirements may be improved by using CSPs to define the desired surface profile (amplitude or roughness).
ICRI has identified 10 distinct profiles produced by the surface preparation methods described in this guideline. As a set, these profiles replicate degrees of roughness considered to be suitable for the application of one or more of the sealer, coating, polymer overlay systems, and/or concrete repair materials. Each profile carries a CSP number ranging from CSP 1 (nearly flat) through CSP 10 (very rough; amplitude greater than 1/4 in. [6 mm]). The profile characteristics for each preparation method are identified by CSP number in the “Profile” section of the method summaries. Molded replicas* of these profiles provide clear visual standards for purposes of specification, execution, and verification. These benchmark profiles may be referenced in specifications, material data sheets, application guidelines, and contract documents to effectively communicate the required surface profile. It is probable that more than one profile will produce acceptable results, and a range of suitable profiles should be specified.
The concrete surfaces shown in Fig. 6.1 to 6.10 were produced using a variety of preparation methods. Although each numbered CSP replica bears the characteristic pattern and texture of the specific preparation method used, each replica is representative of the profile height (amplitude) obtained with all methods identified with the same CSP number.
Figures 6.11 and 6.12 provide a guide to the general appearance of a CSP 10. After preparation is complete, the aggregate should appear clean and crisp and protrude above the paste line a minimum of 1/4 in. (6 mm).
CSP and Protective Systems
The type of protective system or repair material to be applied will impact the type of surface preparation selected. Penetrating sealers will have little or no effect on the appearance of the prepared surface. Any surface defects, contaminants, or profile resulting from the surface preparation will be visible. Thin films may be formulated to achieve high hiding power; however, even relatively minor surface imperfections and profiles produced by surface preparation equipment will be visible. High-build materials will have both high hiding power and some ability to fill irregularities and level the prepared surfaces. A smooth finish over higher profiles may be achieved by increasing the thickness of the applied coating system. Manufacturers of these materials often have minimum thickness requirements, which can be affected by the surface profile. A surface profile greater than specified by the manufacturer may result in an increase in the cost of the system. Overlays and repair materials are generally installed such that the depth of the material covers the amplitude of the surface profile.
Possible surface profiles to be used with various protective systems are given in Table 7.1. Consult the manufacturer to determine the recommended surface profile.
CSP and Preparation Methods
An approximate range of surface profiles obtained using various preparation methods is shown in Table 7.2.
Table 7.1: Protective Systems
Table 7.2: Preparation Methods
(1) Only suitable for freshly placed cementitious materials
Abrasive Blasting
Summary
Abrasive blasting is used to clean and profile concrete surfaces (Fig. 8.1.a). The process can provide a light, clean profile, often referred to as a “brush blast,” or it can be used to achieve a moderate profile. It may also be used to remove surface contaminants and thin, brittle coatings or adhesive films (Fig. 8.1.b) from surfaces and corrosion products from reinforcing steel (Fig. 8.1.c). This method may be used on horizontal, vertical, and overhead surfaces and is suitable for both interior and exterior applications. Both vacuum recovery and wet abrasive blasting equipment are sometimes used to reduce environmental contamination from the abrasive blasting technique. Abrasive blasting is often used to mitigate microcracking caused by other surface preparation methods.
Removal
This method uses a compressed air stream with an abrasive media to clean concrete and steel surfaces. Removal is accomplished by the eroding effect of the blast media impacting the surface at high velocity.
Profile
CSP 2-7—Abrasive blasting should not introduce any noticeable pattern. The profile achieved is dependent on the duration of exposure to the blast stream and the size and cutting efficiency of blast media.
Accessibility
The small size and portability of the hose and blast nozzle provide virtually unrestricted access to all surfaces, including edges, corners, and recessed spaces.
Limitations
Abrasive blast is not recommended for the following:
Environmental factors
Dry abrasive blasting will produce airborne dust containing silica and particles of any material being removed.
Any special requirements for containment and disposal will depend on the specific contaminants or materials being removed. Blast media substitutes such as sodium bicarbonate are sometimes used to reduce the dust hazard or volume of debris. Water may be injected into the blast stream to reduce dust. Vacuum recovery systems may also be used with abrasive blast units to reduce dust and cleanup. Noise levels are likely to exceed 85 dB.
Execution
The blast media stream is directed at the surface using a controlled sweeping motion. The required duration of exposure to the blast stream will depend on the strength of the substrate, air pressure, air volume, blast media type, and degree of cleaning or profiling required. Special provisions are often needed to protect people, property, and the environment from dust and airborne debris. Blast curtains and containment areas may be used to isolate the blast process.
Equipment
Materials
The most common abrasive blast materials are silica sand and slag. There are a wide variety of blast materials available to meet different needs. These materials are consumed in the blast operation and are generally not recycled.
Employee skill level
Medium skill level is required. Special training in safe operation and environmental hazards is required for crew members. A two-person crew per blast unit is required. One crew member will operate the blast nozzle while the other supports the operation by monitoring the blast operation and maintaining the blast media hopper, compressor, and hoses.
Setup and downtime
Time required for mobilization, setup, and maintenance of blast equipment and compressor will take several hours. Significant time may be needed to set up dust protection around the work area.
Cleanup
Dust, fine particles of concrete or other pulverized materials, and blast media are generated by the dry abrasive blast process. The area will require sweeping and/or vacuuming to collect the debris. Dust will accumulate on all unprotected surfaces and will require cleaning. Recuperative or wet abrasive blasting may substantially reduce the volume of dust generated.
Production rates
Productivity is highly variable and is dependent on the strength of the concrete, surface contaminants, accessibility, capacity of blast media hopper, compressor capacity, and type of blast media used. Production rate estimates range from 1000 to 6000 ft2 (100 to 600 m2) per 8-hour shift per unit.
Quality control
Various test techniques are described in Appendix B. The practitioner is encouraged to specify the appropriate test to verify that the desired surface preparation results have been achieved. At a minimum, verify that the CSP required by the specifications has been achieved. Visual inspection should show no dirt, laitance, or debris on the surface. The prepared surface should be free of bond-inhibiting materials. A bond test may be required to demonstrate adequate bond strength. Beads of water may indicate a surface contaminant that could require further surface preparation to achieve a clean surface. ASTM D4259 provides additional considerations for surface preparation and quality control using this method.
Safety hazard
Abrasive blasting will cause the release of dust containing silica. Minimum recommended personal protective equipment (PPE) is as follows:
Consult the material and equipment manufacturer’s current recommended safety procedure. Consult ICRI Technical Guideline No. 120.1 (Sections 2.0 through 7.0) for guidelines and recommendations for safety in the concrete repair industry. Refer to Appendix C for additional information on safety issues related to concrete surface preparation.
Summary
Acid etching is designed to remove cement paste from the surface and surface pores of concrete (Fig. 8.2.a).
Removal
The acid in the etching solution attacks the calcium hydroxide (Ca(OH)2) and calcium silicate hydrate (CSH) in the cement paste, causing rapid deterioration at the surface. The concentration and volume of solution applied are controlled to limit the depth of chemical attack. The typical depth of removal is 0.004 to 0.010 in. (0.1 to 0.25 mm). Etching will remove the cement paste and slightly profile the surface by exposing fine silica aggregate.
Profile
CSP 1-3—Etching should not introduce any noticeable pattern effect on sound concrete surfaces. The surface should feel like fine sandpaper with no residue or grit. The surface should have a dull, even appearance. If the surface is still smooth or glossy, repeat procedure.
Accessibility
The equipment used for this method is portable and maneuverable. Access may be restricted by the presence of nonportable machinery or equipment subject to damage from corrosive mist or splash.
Limitations
Environmental factors
Applied as an acid wash, the mixture may corrode metals on contact. Debris produced by acid etching will contain particles of the material or contaminants being removed. Any special requirements for containment and disposal will depend on the specific materials or contaminant being removed. Spent acid and rinse water must be disposed of as required by local regulations or project restrictions. The acid solution may release toxic vapors.
Execution
Equipment
The use of automatic scrubbing equipment to apply acid etching solution is not generally recommended. However, this equipment is often used to recover etching solution after it has been diluted with rinse water. Consult the equipment manufacturer to determine suitability.
Materials
Labor
Medium to above-medium skill level is required to safely handle and mix hazardous materials and operate equipment.
Setup and downtime
Minimal time is required to mix etching solution. Filling and emptying scrubber and wet-vacuum tanks should take 10 to 20 minutes. Additional time may be required to protect material and equipment in the work area.
Production rates
The rates shown as follows are approximate. Actual rates will vary with the method used, density of surface, dilution ratio, and size of machines.
Quality control
Various test techniques are described in Appendix B. The practitioner is encouraged to specify the appropriate test to verify that the desired surface preparation results have been achieved. At a minimum, verify that the CSP required by the specifications has been achieved. Visual inspection should show no dirt, laitance, or debris on the surface. The prepared surface should be free of bond-inhibiting materials. A bond test may be required to demonstrate adequate bond strength. Beads of water may indicate a surface contaminant that could require further surface preparation to achieve a clean surface. Testing (such as pH testing) should verify that all acid materials have been removed by checking the pH of the rinse water before and after rinsing. ASTM D4260 provides additional considerations for surface preparation and quality control using this method.
Safety hazards
Acid etching involves the use of dangerous chemicals that will cause serious injury if exposed to any part of the body. Always add acid to water, as some acids may react violently if water is added to the acid. The acid may also produce dangerous vapors, which may damage the respiratory system. Operators must be trained in the proper use and handling of the acid materials. Minimum recommended PPE is as follows:
Consult the material and equipment manufacturer’s current recommended safety procedure. Consult ICRI Guideline No. 120.1 (Sections 2.0 through 7.0) for guidelines and recommendations for safety in the concrete repair industry. Refer to Appendix C for additional information on safety issues related to concrete surface preparation.
Summary
Handheld concrete breakers are typically classified by their weight. Larger handheld concrete breakers (jackhammers) in the 30 lb (14 kg) class and larger (Fig. 8.3.a) are typically used on horizontal surfaces, while smaller breakers (chipping hammers) weighing 20 lb (9 kg) or less (Fig. 8.3.b) may be used on horizontal, vertical, and overhead surfaces to remove concrete to a predetermined depth (SHRP-S-336). A typical application for a chipping hammer is the removal of deteriorated and/or chloride-contaminated concrete from around reinforcing steel. Handheld concrete breakers may also be used as an initial step in preparation for overlays. This method is suitable for use in interior and exterior applications.
Removal
Removal is accomplished by the impact of the tool (point or chisel) on the surface. The tools may be pneumatic, electric, or hydraulic. The impact of the tool on the surface will fracture and split the concrete. This will also result in microcracks in the remaining substrate, which will affect the bond of the repair material (Fig. 8.3.c). Surfaces prepared using chipping hammers and handheld concrete breakers will require further preparation (sandblasting, waterblasting, or shotblasting) to remove microcracks in the substrate (Fig. 8.3.d and 8.3.e). The use of heavier handheld concrete breakers will result in deeper microcracking.
Profile
CSP 7-10—Handheld concrete breakers will produce a very irregular surface dominated by fractured coarse aggregate. They will cause microcracks in the substrate and the points and chisel will leave marks on the concrete surface.
Accessibility
Most surfaces are accessible to chipping hammers, while handheld concrete breakers are used on horizontal surfaces.
Limitations
Environmental factors
Handheld concrete breakers will produce airborne dust containing silica and particles of any other materials being removed. Special requirements for disposal of dust and debris will depend on the specific materials or contaminants being removed. Noise levels are likely to exceed 85 dB. Vibration levels are moderate to severe and will transmit through a structure. Vibration of the reinforcing steel may dislodge the reinforcing steel from the surrounding concrete, requiring additional removal to fully expose the reinforcing steel. Work area enclosures and special ventilation provisions may be required indoors to prevent dust intrusion into nearby occupied spaces.
Execution
Handheld concrete breakers are operated by placing the tool against the surface and activating the pneumatic, electric, or hydraulic drive system. When activated, the handheld concrete breaker rapidly impacts the tool (point or chisel) driving the working edge into the concrete surface. The operator controls the depth of removal by observation. The area being chipped will require debris removal to allow the operator to see the removal progress. Further preparation will be required to remove microcracking.
Equipment
Materials
Chisels and points will require periodic sharpening and/ or replacement.
Employee skill level
Operator skill requirements are low.
Setup and downtime
The setup of air hoses and changing tools is required daily. Tool changes for handheld concrete breakers will take 1 minute or less, while chipping hammers will take approximately 5 minutes.
Cleanup
Dust and larger pieces of concrete will be generated from the handheld concrete breaker operation. Sweeping and/or vacuuming will be required to remove the rough debris and fines to allow the operator to see the quality of the removal. Additional cleanup will be required following sandblasting or any other method used as additional surface preparation.
Production rates
Productivity will vary considerably depending on the size of the handheld concrete breaker used, orientation of the surface, strength of substrate, depth of removal, and type of material being removed. The typical removal rate for normal (4000 psi [27.5 MPa]) concrete using a chipping hammer is 1.5 to 4.0 ft3/h (0.04 to 0.11 m3/h) per operator. The removal rate for a handheld concrete breaker is significantly higher depending on the weight of the tool.
Quality control
Various test techniques are described in Appendix B. The practitioner is encouraged to specify the appropriate test to verify that the desired surface preparation results have been achieved. At a minimum, verify that the CSP required by the specifications has been achieved. Visual inspection should show no dirt, laitance, or debris on the surface. The prepared surface should be free of bond-inhibiting materials. A bond test may be required to demonstrate an adequate bond between the prepared surface and repair material. Beads of water may indicate a surface contaminant that could require further surface preparation to achieve a clean surface.
Safety hazards
Handheld concrete breakers will cause dust and produce airborne debris. Minimum recommended PPE is:
Consult the material and equipment manufacturer’s current recommended safety procedure. Consult ICRI Guideline No. 120.1 (Sections 2.0 through 7.0) for guidelines and recommendations for safety in the concrete repair industry. Refer to Appendix C for additional information on safety issues related to concrete surface preparation.
This method removes oil, grease, and other deposits on concrete surfaces by scrubbing with a detergent solution.
Summary
This method may be used on horizontal concrete surfaces to remove dirt, oil, and grease. Corner and edge cleaning can be detailed manually. The scrubbing process should produce clean surfaces devoid of dirt, oil, grease, and loose debris without altering the surface texture. Detergent scrubbing is frequently used to prepare concrete for acid etching.
Removal
Removal is accomplished through the combined action of detergent/chemical cleaners, scrubbing of the surface with brushes (Fig. 8.4.a and 8.4.b), and rinsing or vacuuming of the cleaning solution and debris from the surface (Fig. 8.4.c and 8.4.d). This method is suitable for superficial removal of oil, grease, organic or inorganic residues, wax, rust, and other deposits from concrete surfaces. Absorbed fluids such as oils and grease may require several treatments to achieve acceptable results or may not be adequately removed depending on the nature of the absorbed fluid and depth of penetration.
Profile
CSP 1—Detergent scrubbing will not produce any noticeable pattern effect on sound concrete surfaces.
Accessibility
With the variety of portable and maneuverable equipment available, most surfaces are accessible. Access to corners, recesses, and between penetrations is restricted by the reach and arc of the brushes. These areas may be addressed manually.
Limitations
This method is limited to the removal of water-soluble or detergent-emulsifiable contaminants and debris, which can be readily loosened by light mechanical action of the scrubbers. Note that in heavily contaminated substrates, additional contaminants may diffuse to the cleaned surface within hours/days of cleaning.
Environmental factors
Moderate-to-heavy contamination may produce significant amounts of sludge or other debris. Some debris may be considered hazardous or otherwise unqualified for discharge into sewer systems. Debris produced by detergent scrubbing will contain particles of the material or contaminants being removed. Any special requirements for containment and disposal will depend on the specific materials or contaminant being removed. Suitable measures for the containment, collection, and proper disposal of debris and rinse water should be considered. Detergents and cleaning chemicals may produce odors.
Execution
Equipment
Manual methods:
Mechanical methods:
Materials
Labor
Low skill is required for manual scrubbing method. Medium skill is required to operate automatic scrubber and mix chemical solutions.
Setup and downtime
Cleanup
Scrubbing manually with brooms or mechanically with electric single-disc machines will generate a liquid residue that must be removed by a squeegee, vacuum, or lowpressure water cleaning method to obtain a clean surface. Automatic scrubbers have an internal squeegee/vacuum system to collect the liquid residue immediately behind the scrub brushes.
Production rates
The following rates are approximate. Actual rates will vary considerably with the severity of soil, size of machine, and effectiveness of chemical solution being used.
Quality control
Various test techniques are described in Appendix B. The practitioner is encouraged to specify the appropriate test to verify that the desired surface preparation results have been achieved. At a minimum, verify that the CSP required by the specifications has been achieved. Visual inspection should show no dirt, laitance, or debris on the surface. The prepared surface should be free of bondinhibiting materials. A bond test may be required to demonstrate adequate bond strength. Beads of water may indicate a surface contaminant that could require further surface preparation to achieve a clean surface. ASTM D4258 provides additional considerations for surface preparation and quality control using this method.
Safety hazards
Operators must be trained in the proper use of this equipment and the proper handling of the cleaning solutions. Minimum recommended PPE is as follows:
Consult the material and equipment manufacturer’s current recommended safety procedure. Consult ICRI Guideline No. 120.1 (Sections 2.0 through 7.0) for guidelines and recommendations for safety in the concrete repair industry. Refer to Appendix C for additional information on safety issues related to concrete surface preparation.
Summary
This method may be used on horizontal, vertical, and overhead surfaces to smooth slight surface irregularities and remove thin coatings and rigid high-build coatings such as epoxy, polyurethane, and methacrylate coatings. Grinding may also be used to remove mineral deposits, efflorescence, rust, and other deposits. Grinding may be used on almost any substrate and is suitable for interior and exterior applications.
Removal
Removal is accomplished by the rotation of one or more abrading stones or discs applied under pressure at right angles to the concrete surface. The grinding stone or disc is moved across the surface until the desired effect is achieved.
Profile
CSP 1-2—Grinding produces a smooth surface. Other methods may be used in conjunction with grinding to provide the required profile. Small handheld grinders are likely to produce gouging and a circular, grooved pattern. Walk-behind units will eliminate gouging but are likely to show a circular pattern. Larger units using fine stones should not produce any detectable pattern and are frequently used for producing polished concrete and terrazzo.
Accessibility
Most surfaces, including edges, are accessible. Equipment ranges from small handheld grinders to walk-behind units with multiple discs. Access to corners and tight configurations is restricted by the arc of the grinding disc.
Limitations
Grinding is not recommended for the following applications:
Environmental factors
Dry grinding will produce a dust containing silica and other contaminants being removed from the surface. Dust may be minimized with vacuum systems attached to the grinder (Fig. 8.5.a, 8.5.c, and 8.5.d). Debris generated by this method will contain fine particles of any material or contaminant being removed. Wet grinding, which may be used to minimize airborne dust, will produce a slurry residue and rinse water that will require proper disposal. Grinding soft, easily charred materials will generate smoke, which may be hazardous. Noise and vibration levels are considered to be low.
Execution
Grinders are moved over the surface in a linear or sweeping motion until the desired removal or effect is achieved.
Equipment
Grinders are available in electric-, pneumatic-, or gasdriven models. Sizes range from walk-behind machines (Fig. 8.5.a to 8.5.c) to handheld grinders (Fig. 8.5.d). Rotation speeds vary from 1000 to 9000 rpm. Grinders are typically connected to a vacuum dust recovery system.
Materials
The grinding medium (stone or disc) is consumed during the process. Some discs have inserts that may be changed as they wear out. Grinding discs range in diameter from 4 to 18 in. (100 to 450 mm). Their composition varies from very fine polishing media to aggressive cutting media with wet or dry diamonds. The disc shape may be flat, cone-shaped, or cup-shaped.
Employee skill level
Low to medium skill is required.
Setup and downtime
Setup requires very little time unless dust protection includes draping and taping. Changing stones or discs is quick. Frequency of replacement will depend on the composition of the stone or disc, substrate, and material being removed.
Cleanup
Grinding will produce a fine powder and small chips. The debris can be swept, rinsed with water, or vacuumed.
Production rates
Productivity will vary depending on the grinding media selected and the type of material being removed. Estimated rates are:
Quality control
Various test techniques are described in Appendix B. The practitioner is encouraged to specify the appropriate test to verify that the desired surface preparation results have been achieved. At a minimum, verify that the CSP required by the specifications has been achieved. Visual inspection should show no dirt, laitance, or debris on the surface. The prepared surface should be free of bondinhibiting materials. A bond test may be required to demonstrate adequate bond strength. Beads of water may indicate a surface contaminant that could require further surface preparation to achieve a clean surface. ASTM D4259 provides additional considerations for surface preparation and quality control using this method.
Safety hazards
Grinding will cause the release of dust. Minimum recommended PPE is as follows:
Consult the material and equipment manufacturer’s current recommended safety procedure. Consult ICRI Guideline No. 120.1 (Sections 2.0 through 7.0) for guidelines and recommendations for safety in the concrete repair industry. Refer to Appendix C for additional information on safety issues related to concrete surface preparation.
(5000 to 45,000 psi [35 to 275 MPa] at 2 to 50 gal./min [8 to 190 L/min])
Summary
High- and ultra-high-pressure water jetting may be used to remove laitance, efflorescence, scale, dirt, or other contaminants. With suitable pressure and a nozzle, epoxy, urethane, and methacrylate coatings and thin overlay systems may be removed (Fig. 8.6.b, 8.6.c, and 8.6.d). It may also be used to remove carbonated, freezing-and-thawing-damaged, weakened, delaminated, or otherwise undesirable concrete from the substrate. The method is suitable for horizontal, vertical, and overhead applications. Pressures in the higher ranges may be needed to remove certain coating materials. This method will clean the reinforcing steel; however, flash rust may occur. High-pressure water jetting may be used for hydrodemolition (refer to ICRI Guideline No. 310.3; SHRP-S-336).
Removal
Removal is accomplished when the water jet strikes the surface. The degree of removal is controlled by the force of the water jet (pressure and volume) and the length of time the water jet is in contact with the surface. Multi-jet systems rotating at a high speed (1000 to 3000 rpm) spread the force of the water over a larger area and result in minimal contact time with the surface. The multi-jet systems are effective in removing surface contaminants, including coatings and weakened concrete. A single water jet rotating at slower speeds (300 to 900 rpm) or oscillating concentrates the force of the water and produces a longer contact time with the surface, resulting in more aggressive removal. The single-jet systems are effective in removing sound and unsound concrete.
Profile
CSP 3-10—When using multi-jet tools, the surface profile of sound concrete may remain largely unaffected by this process. The use of multi-jet heads and a short contact time will clean the surface while creating a minimal profile (CSP 3). Pressure and nozzle tips may be adjusted to produce the desired profile. The use of high- and ultra-high-pressure water jetting on low-strength or deteriorated surfaces will produce a much more aggressive profile as surface defects are removed. The use of a single nozzle will result in a surface profile of CSP 10. The amplitude of ±1/2 the diameter of the coarse aggregate can be expected (ICRI 310.3).
Accessibility
With the wide variety of portable and maneuverable equipment available, most surfaces are easily accessible. Tight spaces can be accessed with a handheld lance.
Limitations
This method should not be used where goods or equipment may be damaged by impact from water jets or where they cannot be protected from heavy mist or flooding. Proper precautions for live electrical wiring or conduit need to be considered when using high-/ultra-high-pressure water.
Environmental factors
This process produces loud noise. Mist and a significant volume of water will be introduced into the work area. The volume of water introduced will range from 2 to 50 gal./ min (8 to 150 L/min) and is determined by the type of removal to be performed and the requirements of the equipment selected. Environmental regulations may require containment and regulated disposal of the liquid waste generated. Frequently, the pH of the spent hydrodemolition water and suspended solids are adjusted prior to disposal.
Execution
The concrete surface is prepared by uniformly moving the water jet back and forth over the surface until the desired results are achieved. Automated equipment typically moves the nozzle(s) left and right as the unit advances. Standing water may need to be pumped or squeegeed off the surface. Units that clean and recycle jetting water are available. Solid debris, slurry, and water residue are disposed of as required by local regulations or project restrictions.
Equipment
Materials
Potable water is recommended and may be provided from a fire hydrant connection, tanker, or similar source capable of meeting the requirements of the equipment.
Employee skill level
Medium to above-medium skill level with appropriate training is required. Must be able to maintain high-pressure pumps and components and safely operate equipment. Skilled supervision may be needed if complex equipment is used. Everyone operating high- or ultra-high-pressure waterblasting equipment must be trained in the hazards of this type of equipment.
Setup and downtime
Setup time is variable depending on the size of the work area and specific protective measures required. Downtime may be required to maintain equipment and replace consumable parts, such as nozzles and seals.
Cleanup
Collect water for proper disposal. Debris can be rinsed, swept, or vacuumed from the surface. Jetting of deteriorated surfaces may produce additional debris.
Production rates
The rates shown as follows are approximate and assume sound, 4000 psi (28 MPa) concrete. Actual production rates will vary considerably and will depend on the strength of the concrete, hardness and bond strength of material to be removed, preparation objectives, operator skill, and efficiency of equipment employed.
Quality control
Various test techniques are described in Appendix B. The practitioner is encouraged to specify the appropriate test to verify that the desired surface preparation results have been achieved. At a minimum, verify that the CSP required by the specifications has been achieved. Visual inspection should show no dirt, laitance, or debris on the surface. The prepared surface should be free of bond-inhibiting materials. A bond test may be required to demonstrate adequate bond strength. Beads of water may indicate a surface contaminant that could require further surface preparation to achieve a clean surface.
Safety hazards
Water jetting will create a dangerous water stream, loud noise, flying debris, and water spray. A water jet cut or puncture can force bacteria into the body, resulting in a serious infection. Operators must be trained in the proper use of this equipment. Minimum recommended PPE is:
Consult the material and equipment manufacturer’s current recommended safety procedure. Consult ICRI Guideline No. 120.1 (Sections 2.0 through 7.0) for guidelines and recommendations for safety in the concrete repair industry. Refer to Appendix C for additional information on safety issues related to concrete surface preparation. Consult ASTM E1575, ICRI 310.3, and WJTA for safety practices for pressure water cleaning.
1000 to 5000 psi (7 to 35 MPa) at 2 to 10 gal./min (8 to 40 L/min)
Summary
This method may be used outdoors to remove dust, friable materials, debris, or water-soluble contaminants from concrete surfaces and surface cavities (Fig. 8.7.a to 8.7.c). It may be used in interior spaces where mist, noise, and standing water can be tolerated. The method is suitable for horizontal, vertical, and overhead applications. For surface preparation applications, low-pressure water cleaning is often used to perform a final rinse following other surface preparation techniques.
Removal
Water is sprayed at pressures less than 5000 psi (35 MPa) to remove dirt and loose, friable material. This method does not remove any significant amount of concrete.
Profile
CSP 1—This method does not produce any significant texture, profile, or pattern on sound concrete.
Accessibility
Most low-pressure water cleaning is performed with a handheld lance and is readily accessible to all surfaces.
Limitations
The presence of materials or equipment that cannot be adequately protected from mist or spray may restrict use of this method. This method is not suitable for the removal of sealers, coatings, curing membranes, or any concrete other than what is already loose.
Environmental factors
Mist and a large volume of water will be introduced into the work area. Debris produced by low-pressure water cleaning will contain particles of material or contaminants being removed. Any special requirements for containment and disposal will depend on the specific materials or contaminant being removed. Environmental regulations may require containment and regulated disposal of the liquid waste generated.
Execution
Equipment
Materials
Water source may be provided by tanker, hydrant connection, industrial spigot, or pump.
Labor
Work may be performed with unskilled labor. Skilled supervision may be needed if complex equipment is used.
Setup and downtime
Equipment setup time is very short but additional time may be necessary to protect surfaces and install runoff protection to catch loosened materials.
Cleanup
Low-pressure water cleaning is often used to clean up following other surface preparation techniques or repair procedures. Water and debris produced during the cleaning will have to be contained, collected, and disposed of.
Production rates
The rates that follow are approximate. Actual rates will vary with the pressure, volume of water, type of spray nozzle, number of passes, speed of travel, and efficiency of equipment employed and preparation objectives.
Quality control
Various test techniques are described in Appendix B. The practitioner is encouraged to specify the appropriate test to verify that the desired surface preparation results have been achieved. At a minimum, verify that the CSP required by the specifications has been achieved. Visual inspection should show no dirt, laitance, or debris on the surface. The prepared surface should be free of bond-inhibiting materials. A bond test may be required to demonstrate adequate bond strength. Beads of water may indicate a surface contaminant that could require further surface preparation to achieve a clean surface. ASTM D4259 provides additional considerations for surface preparation and quality control using this method.
Safety hazards
Low-pressure water cleaning will create a dangerous water stream, loud noise, flying debris, and water spray. A water spray may cut or puncture the skin and can force bacteria into the body, resulting in a serious infection. Operators must be trained in the proper use of this equipment. Minimum recommended PPE is as follows:
Consult the material and equipment manufacturer’s current recommended safety procedure. Consult ICRI Guideline No. 120.1 (Sections 2.0 through 7.0) for guidelines and recommendations for safety in the concrete repair industry. Refer to Appendix C for additional information on safety issues related to concrete surface preparation. Consult ASTM E1575, ICRI 310.3, and WJTA for safety practices for pressure water cleaning.
Summary
Rotomilling is used on horizontal surfaces to remove unsound concrete, mastics or other high-build coatings, and asphaltic materials (Fig. 8.8.d). It may also be used to profile concrete substrates (Fig. 8.8.c). This method is suitable for use in interior and exterior applications, primarily on horizontal surfaces. Milling attachments mounted to excavators are used for milling vertical surfaces and corners.
Removal
The rotomilling equipment contains a rotating drum with teeth (Fig. 8.8.b). As the machine moves forward, the cutting teeth strike the surface with great force, fracturing material into chips and dust. The depth of concrete removal ranges from 1/4 to 4 in. (6 to 100 mm). The machine’s maximum removal depth is determined by the number and size of teeth, and the size and weight of the machine. A greater number of small teeth will produce a smoother surface CSP 6 to 7, while fewer, larger teeth will produce a CSP 9 and greater. The weight of the machine provides the downward force on the cutting drum. Most machines are equipped with depth gauges, which allow the operator to adjust and monitor the depth of removal.
Profile
CSP 6 to 9—Rotomilling will produce a rough surface with fractured coarse aggregate. The teeth of the rotating drum will produce a pattern with linear striations (grooving). The profile obtained is determined by the number and size of teeth. The prepared surface may be very rough and can exceed CSP 9. This method will cause microcracking in the prepared surface.
Accessibility
Most rotomilling equipment will reach within 6 in. (150 mm) of vertical surfaces such as walls, curbs, and columns.
Limitations
Supported slabs must be structurally capable of supporting large, heavy equipment. This method will produce high levels of noise, dust, and vibration. Rotomilling operations will cause microcracking. The deleterious effects of microcracking may be reduced or eliminated by following initial removal with steel shotblasting, abrasive blasting, or high- and ultra-high-pressure water jetting. The depth of microcracking may be deeper than can be readily addressed by abrasive blasting or shotblasting.
Environmental factors
Rotomilling will produce airborne dust containing concrete and particles of any other materials or contaminants being removed. Requirements for containment and disposal of dust and debris will depend on the specific materials or contaminants being removed. Special ventilation provisions may be required when operating gasoline- or diesel-powered units indoors. Water that is used to control dust or clean the substrate may need to be collected and treated prior to disposal. Noise levels will exceed 85 dB. Rotomilling equipment operation results in significant vibration to the structure.
Execution
The surface is prepared by driving the rotomilling equipment in a straight path across the surface. The depth is controlled by adjusting the depth of the drum.
Equipment
Large rotomilling machines are self-propelled ride-on units that collect the debris on a conveyor and transport it to a container, usually a dump truck working with the rotomill. Smaller units consist of a special rotomilling head mounted on a skid-steer loader (Fig. 8.8.a). A rotomilling head mounted on an excavator may be used for vertical or overhead removal.
Materials
Teeth mounted on the rotomilling drum.
Employee skill level
Experienced, trained machine operators are needed to operate equipment and perform periodic maintenance or replacement of cutting heads and teeth. Additional workers with appropriate skills are needed to operate the support equipment, such as conveyors, dump trucks, microcrack mitigation equipment, and for general cleanup.
Setup and downtime
Machines arrive at the site ready to work. Downtime may be experienced as a result of periodic maintenance and replacement of teeth.
Cleanup
Debris removal equipment may include dump trucks, loaders, a conveyor system, shovels, and brooms. Large machines will convey the debris directly into a dump truck. Smaller units leave the debris on the surface, which is removed using skid-steer loaders, brooms, and shovels.
Production rates
The removal rate will depend on the depth and hardness of the substrate concrete. Estimated removal rates are:
Quality control
Various test techniques are described in Appendix B. The practitioner is encouraged to specify the appropriate test to verify that the desired surface preparation results have been achieved. At a minimum, verify that the CSP required by the specifications has been achieved. Visual inspection should show no dirt, laitance, or debris on the surface. The prepared surface should be free of bond-inhibiting materials and microcracking. A bond test may be required to demonstrate adequate bond strength. Beads of water may indicate a surface contaminant that could require further surface preparation to achieve a clean surface.
Safety hazards
Rotomilling creates dust, flying debris, and loud noise. Operators must be trained in the proper use of this equipment. Minimum recommended PPE is as follows:
Consult the material and equipment manufacturer’s current recommended safety procedure. Consult ICRI Guideline No. 120.1 (Sections 2.0 through 7.0) for guidelines and recommendations for safety in the concrete repair industry. Refer to Appendix C for additional information on safety issues related to concrete surface preparation.
Summary
Needle scaling tools are primarily used for metal cleaning (Fig. 8.9.d); however, they are also used in concrete and masonry surface preparation (Fig. 8.9.c). This method can be used on surfaces indoor, outdoor, or underwater and on surfaces of any orientation to remove efflorescence, brittle encrustations, and coating systems. It is frequently used for work on edges and other tight spaces that cannot be accessed by larger, more automated equipment. It may be used underwater to remove barnacles and other marine shellfish attached to submerged surfaces.
Removal
Removal is accomplished by the superficial fracturing and pulverization of the concrete surface. The surface is impacted by the pointed tips of a bundle of steel rods that are pulsed by compressed air or hydraulics.
Profile
CSP 2 to 4—Needle scaling will produce random, evenly distributed impact craters around larger aggregate, imparting a textured surface.
Accessibility
Handheld needle scaling tools are available in several sizes, providing virtually unrestricted accessibility.
Limitations
Needle scaling is not recommended for removal of coatings that are thick or resilient, preparation of large surface areas, or the removal of sound concrete. Needle scaling may produce microcracking of the surface.
Environmental factors
Needle scaling will produce dust containing silica and particles of any material or contaminants being removed. Any special requirements for containment and disposal will depend on the specific contaminants being removed. Noise levels are loud and vibration levels are low to medium.
Execution
The needle scaling tool is held against the surface with light-to-medium pressure. The pneumatically driven rods are activated by a trigger located in the unit’s handle.
Equipment
Materials
The hardened steel rods are consumed during surface preparation.
Employee skill level
Low skill is required.
Setup and downtime
Minimal. Approximately 5 minutes per hour to change needle bundles. Rebuilding needle bundles is usually an off-site activity.
Cleanup
Needle scaling will generate dust and small airborne particles. The tools are not equipped to collect debris, which may be vacuumed or swept up for proper disposal.
Production rates
Productivity will range from 10 to 50 ft2/h (1 to 5 m2/h). Rate is dependent on size of needle gun, number of needles per bundle, available air pressure and volume, strength of substrate, and hardness of material being removed.
Quality control
Various test techniques are described in Appendix B. The practitioner is encouraged to specify the appropriate test to verify that the desired surface preparation results have been achieved. At a minimum, verify that the CSP required by the specifications has been achieved. Visual inspection should show no dirt, laitance, or debris on the surface. The prepared surface should be free of bondinhibiting materials. A bond test may be required to demonstrate adequate bond strength. Beads of water may indicate a surface contaminant that could require further surface preparation to achieve a clean surface. ASTM D4259 provides additional considerations for surface preparation and quality control using this method.
Safety hazards
Needle scaling tools will cause the release of dust. Minimum recommended PPE is as follows:
Consult the material and equipment manufacturer’s current recommended safety procedure. Consult ICRI Guideline No. 120.1 (Sections 2.0 through 7.0) for guidelines and recommendations for safety in the concrete repair industry. Refer to Appendix C for additional information on safety issues related to concrete surface preparation.
Summary
Scabbling is used primarily on horizontal surfaces to remove concrete or brittle coatings such as epoxy, polyurethane, or methyl methacrylate systems up to 1/4 in. (6 mm) thick (Fig. 8.10.a) in preparation for overlays. It may also be used to deeply profile concrete surfaces. Handheld units (bush hammers) are available for vertical and overhead surfaces. This method is suitable for use in interior and exterior applications.
Removal
Removal is accomplished by the impact of the scabbling head (Fig. 8.10.b) on the surface. The piston-driven cutting heads are pneumatically activated. Repeated blows to the surface result in chipping and crushing of the concrete surface and material being removed.
Profile
CSP 7 to 9—Scabbling will produce a very irregular surface dominated by fractured coarse aggregate. Scabbling will cause microfractures in the substrate. There should be no discernible tool pattern.
Accessibility
Most surfaces are accessible using equipment ranging from small handheld to large walk-behind units. Corners, recesses, and tight configurations are accessible with handheld tools (bush hammers).
Limitations
Scabbling is not recommended for the removal of elastomeric membranes or gummy materials such as tile or carpet adhesives.
Environmental factors
Scabbling will produce airborne dust containing silica and particles of any other materials being removed. Any special requirements for containment and disposal of dust and debris will depend on the specific materials or contaminants being removed. Noise levels are likely to exceed 85 dB. Vibration levels are moderate to severe and will transmit through a structure. Work area enclosures and special ventilation provisions may be required indoors to prevent dust intrusion into nearby occupied work space.
Execution
Scabblers are operated by manually pushing the units across the surface in a back-and-forth motion at slow speed. The area being scabbled will require continuous debris removal to allow the operator to see the removal progress.
Equipment
Materials
Impact bits are the consumed material (Fig. 8.10.b). These are available in varying configurations with tungsten carbide inserts.
Employee skill level
Operator skill requirements are low.
Setup and downtime
Setup of air hoses and changing bits is required once per day. Bit changes will take anywhere from 10 minutes for single-head units to as much as 35 minutes for large, multi-head units.
Cleanup
Dust and larger particles up to 1/2 in. (13 mm) in diameter will be generated from the impact of the bits. Sweeping and/or vacuuming will be required to continuously remove the rough debris and fines to allow the operator to see the quality of the removal.
Production rates
Productivity will vary considerably depending on the size of the machine, strength of substrate, depth of removal, and type of material being removed. For heavy removal, estimated rates range from 20 to 100 ft2/h (1.9 to 9.3 m2/h).
Quality control
Various test techniques are described in Appendix B. The practitioner is encouraged to specify the appropriate test to verify that the desired surface preparation results have been achieved. At a minimum, verify that the CSP required by the specifications has been achieved and microcracking has been mitigated. Visual inspection should show no dirt, laitance, or debris on the surface. The prepared surface should be free of bond-inhibiting materials. A bond test may be required to demonstrate adequate bond strength. Beads of water may indicate a surface contaminant that could require further surface preparation to achieve a clean surface. ASTM D4259 provides additional considerations for surface preparation and quality control using this method.
Safety hazards
Scabblers will cause the release of dust and will produce airborne debris. Minimum recommended PPE is:
Consult the material and equipment manufacturer’s current recommended safety procedure. Consult ICRI Guideline No. 120.1 (Sections 2.0 through 7.0) for guidelines and recommendations for safety in the concrete repair industry. Refer to Appendix C for additional information on safety issues related to concrete surface preparation.
Summary
Scarification is used primarily on horizontal surfaces for the removal of concrete and brittle coatings up to 1/8 in. (3 mm) thick. Multiple passes may be made for deeper removal. It may also be used to profile concrete surfaces (Fig. 8.11.c). Adhesives may be removed by the adjustment of spacers and the selection of appropriate cutters. Handheld units are available for vertical and overhead applications. Scarifying may be used on almost any concrete substrate and is suitable for both interior and exterior applications. This method is also known as concrete planing.
Removal
Removal is accomplished by the rotary action of cutters (toothed washers) on the surface to fracture or pulverize the concrete. The cutters are assembled on steel rods mounted at the perimeter of a drum that rotates at high speeds. Removal depth may range from light surface profiling to 1/4 in. (6 mm) for smaller equipment and 1/2 to 3/4 in. (13 to 19 mm) for larger equipment. Removal depths greater than 1/8 in. (3 mm) are accomplished in multiple passes.
Profile
CSP 4 to 7—Scarifying will produce a parallel, striated pattern. The deepest removal pattern will be produced at surface high points.
Accessibility
With portable equipment ranging in size from small handheld devices to large, self-propelled units, most surfaces are accessible to within 1/4 in. (6 mm) of the edge. Access to corners and tight configurations such as around and between pipes is restricted by the dimensions of the drum housing.
Limitations
Scarification is not recommended for surface preparation for sealers or coatings less than 15 mils (0.38 mm) thick or the removal of heavy elastomeric membranes. This method may cause microcracking in the substrate.
Environmental factors
Scarifying will produce airborne dust containing concrete and particles of the material being removed. Any special requirements for containment and disposal of dust and debris will depend on the specific contaminants being removed. Noise levels are likely to exceed 85 dB. Vibration levels are moderate. Ventilation may be required when operating gasoline- or diesel-powered units indoors.
Execution
With the exception of handheld units, most scarifiers are operated by pushing the machine forward over the surface, advancing at a slow walk. The depth and rate of removal are adjusted by raising or lowering the drum to increase or decrease the impact of the cutters. Several passes may be required to achieve the desired profile. Debris must be removed after each pass.
Equipment
Materials
The cutters are consumed during the removal (Fig. 8.11.b). The rate of consumption depends on the following:
Labor
Low to medium skill is required.
Setup and downtime
Minimal. Setup requires very little time. Drum changes will take approximately 5 to 10 minutes. Rebuilding drums is usually done off-site.
Cleanup
Sweeping and removal of the dust and debris will be required.
Production rates
The rates shown as follows are estimates. Productivity will vary considerably depending on equipment size, depth of removal, and type of material being removed.
Quality control
Various test techniques are described in Appendix B. The practitioner is encouraged to specify the appropriate test to verify that the desired surface preparation results have been achieved. At a minimum, verify that the CSP required by the specifications has been achieved and that the concrete has no bruising (microcracking). Visual inspection should show no dirt, laitance, or debris on the surface. The prepared surface should be free of bond-inhibiting materials. A bond test may be required to demonstrate adequate bond strength. Beads of water may indicate a surface contaminant that could require further surface preparation to achieve a clean surface. ASTM D4259 provides additional considerations for surface preparation and quality control using this method.
Safety hazards
Mechanical scarifiers will produce dust. If gas- or dieselpowered equipment is used, the area should be wellventilated. Minimum recommended PPE is as follows:
Consult the material and equipment manufacturer’s current recommended safety procedure. Consult ICRI Guideline No. 120.1 (Sections 2.0 through 7.0) for guidelines and recommendations for safety in the concrete repair industry. Refer to Appendix C for additional information on safety issues related to concrete surface preparation.
Summary
Shotblasting is principally used to clean and profile horizontal surfaces in preparation for the application of sealers, coatings, or polymer overlays. This method is also used to remove dirt, laitance, curing compounds, sealers, or other superficial contaminants and some existing coatings and adhesives (Fig. 8.12.c). Handheld machines are available for use on vertical surfaces. Shotblasting is suitable for use in both interior and exterior applications.
Removal
Removal is accomplished by the pulverizing effect of a steel shot impacting the surface at high velocity. The steel shot is propelled against the surface (Fig. 8.12.b—red arrows) by a rotating wheel. The steel shot and removed material (Fig. 8.12.b—yellow arrows) are collected with the aid of a dust collection system. The removed material is separated as waste and the steel shot is reused. The depth of removal is controlled by shot size, number of repeated passes, and rate of linear travel.
Profile
CSP 2 to 9—As the depth of removal increases, the profile will be increasingly dominated by the size and shape of the coarse aggregate.
Accessibility
Shotblasting equipment is available in a range of sizes to provide ready access to most surfaces. Removal widths range from 5 to 48 in. (130 mm to 1.2 m). Edges and corners may be detailed to within 1/4 in. (6 mm) of the vertical surfaces with specialty edging machines or handheld units.
Limitations
This method is generally not suitable for removing uncured resin systems and resilient or tar-based materials. Overlapping passes may lead to a stripping pattern with deeper removal in the overlap area.
Environmental factors
Shotblast systems produce very little airborne dust or contamination. Most models can be fitted with a filter to further lower the level of airborne dust produced. Debris produced by shotblasting will contain particles of material or contaminants being removed. Any special requirements for containment and disposal will depend on the specific materials or contaminant being removed. Special ventilation provisions may be required when operating gasoline-, diesel-, or propane-powered units indoors. The noise factor may exceed 85 dB. Vibration is not considered to be a factor.
Execution
Shotblasting provides a uniform cleaning pattern across the width of the machine. The machine is steered in a straight line across the surface. At the end of each pass, the machine is turned around and steered parallel to the previous path with minimum overlap. Some overlap is required to prevent the development of unprepared strips between passes.
Equipment
Materials
Steel shot is the consumed material. Consumption ranges from 10 to 20 lb/h (5 to 9 kg/h). The typical size of the steel shot is shown as follows:
Labor
Individuals operating the equipment should be experienced and well-trained. An individual with intermediate mechanical skills can operate and maintain most shotblast systems. Large, electrically powered machines require connection to a three-phase, high-voltage power source that may require a licensed electrician.
Setup and downtime
Surfaces must be dry and broom-cleaned prior to shotblasting. Electrical equipment must be connected to an adequate power source. A test area is required to ensure that media size and machine adjustment will achieve desired performance. Replacement of worn blasting wheels and liners is required every 20 to 40 hours and will take 20 to 45 minutes. Equipment is shut down every 30 to 60 minutes to remove debris from the collection system.
Cleanup
Steel shot may remain on the surface, in edges or corners, or trapped in cracks. It may be recovered by using magnets, a magnetic broom, air blasting, a vacuum, or a stiff-bristle broom.
Production rates
The following rates are approximate and assume a sound horizontal concrete surface. Actual production rates may vary considerably and depend on the strength of the concrete, the type of material being removed, preparation objectives, operator skill, and efficiency of equipment employed.
Quality control
Various test techniques are described in Appendix B. The practitioner is encouraged to specify the appropriate test to verify that the desired surface preparation results have been achieved. At a minimum, verify that the CSP required by the specifications has been achieved. Visual inspection should show no dirt, laitance, or debris on the surface. The prepared surface should be free of bond-inhibiting materials. A bond test may be required to demonstrate adequate bond strength. Beads of water may indicate a surface contaminant that could require further surface preparation to achieve a clean surface.
Safety hazards
Shotblasting may cause the release of high-velocity steel shot. If gas- or diesel-powered equipment is used, the area should be well-ventilated. Minimum recommended PPE is:
Consult the material and equipment manufacturer’s current recommended safety procedure. Consult ICRI Guideline No. 120.1 (Sections 2.0 through 7.0) for guidelines and recommendations for safety in the concrete repair industry. Refer to Appendix C for additional information on safety issues related to concrete surface preparation.
Summary
Concrete surface hydration retarders may be used to remove the surface of unhydrated cement following concrete placement. The process exposes the aggregate and provides a deep profiled textured finish for bonding materials such as epoxies and cementitious grouts, toppings, and overlays (Fig. 8.13.c and 8.13.d). Surface retarders may be used to provide a light profile for rapid-hardening concrete, sprayapplied mortars, or shotcrete. They are suitable for freshly placed, sloped, and horizontal surfaces. Some specialty types of surface retarders are designed to apply to formwork prior to concrete placement to achieve an architectural finish or a profiled surface for construction joints.
Removal
This method involves the application of a material that temporarily inhibits the surface hydration of freshly placed concrete or mortar. The retarder is washed off within several days following application to provide a high-profile, textured surface. This method does not cause microcracking.
Profile
CSP 5 to 10—Surface hydration retarders produce a range of profiles depending on the following factors:
Retarders may be used to produce a CSP 10 for the application of monolithic toppings, additional layers of shotcrete or spray-applied mortar, and epoxy or cementitious grouts. The surface hydration retarder should not produce any noticeable pattern.
Accessibility
The surface retarder may be used on any surface that can be accessed prior to hardening of the freshly placed concrete or mortar. The surface retarder may have to be covered, which could affect accessibility. Formwork retarders should typically be allowed to dry prior to concrete or mortar placement.
Limitations
Surface hydration retarders are suitable for application to freshly placed cementitious concrete or mortar. They should not be used on:
Environmental factors
Surface hydration retarders will produce wash water that will have a pH similar to that of the freshly placed concrete or mortar (pH 12 to 13.5). The chemical composition of the retarder may require additional precautions (consult the manufacturer’s material safety data sheet [MSDS]).
Execution
Follow the manufacturer’s recommendation for mixing and application of the retarder. Apply the surface hydration retarder immediately following placement of fresh concrete or mortar by evenly spraying the liquid material onto the surface in accordance with the manufacturer’s instructions (Fig. 8.13.a).
For spray-on surface types, prevent the surface from drying by covering the surface with polyethylene, burlap/ polyethylene laminate, or other impervious sheet covering. For formwork retarders, allow to dry or harden in accordance with the manufacturer’s instructions.
Allow the concrete to cure sufficiently to resist the effects of the washing of the unhydrated surface material (typically overnight). Retarders slow the hydration process but do not stop it and need to be removed before the surface can harden and prevent removal (typically remove within 4 days following application). Periodic inspections are needed to determine the amount of hardening that has occurred to determine the timing of the removal of the unhydrated material.
The retarder and unhydrated cement may be removed using potable water with a garden-hose nozzle or a pressure washer with sufficient power to expose the aggregate (Fig. 8.13.b and 8.13.c). Rinse until the washing water runs clear. Dispose of the debris and wash water in accordance with state and local requirements. Overspray of the surface hydration retarder can usually be removed by rinsing with water.
Equipment
A sprayer is recommended to evenly apply the retarder material. A garden hose or pressure washer should be used to remove the retarder and unhydrated material following curing.
Materials
Surface hydration retarder and polyethylene, burleen, or other impervious sheet film for curing of the system.
Employee skill level
Low skill is required for application and removal. Moderate skill is required to assess proper timing of removal.
Setup and downtime
Minimum setup is required for preparing the retarder for application. Time must be allowed for the concrete or mortar to cure sufficiently to allow the removal of the unhydrated material to the desired depth.
Cleanup
Cleanup and disposal of rinse water and unhydrated material will be required. Incidental overspray during the washing operation may require precautions for flying debris caused by pressure washing.
Production rates
Productivity is very high. Limiting factors are typically determined by the accessibility of the application area to the surface hydration retarder spray, the amount of area that can be covered with the film after surface hydration retarder application, and the labor involved in washing off and disposal of the material and wash water. The production rate is estimated at 300 to 1000 ft2/h (28 to 93 m2/h) depending on placement configuration.
Quality control
Various test techniques are described in Appendix B. The practitioner is encouraged to specify the appropriate test to verify that the desired surface preparation results have been achieved. At a minimum, verify that the CSP required by the specifications has been achieved. Visual inspection should show no dirt, laitance, or debris on the surface. The prepared surface should be free of bond-inhibiting materials. A bond test may be required to demonstrate adequate bond strength.
Safety hazards
Surface retarders are chemicals that may cause injury if exposed to any part of the body. In addition, water will be used to rinse the unhydrated material from the surface. This rinse water will be highly alkaline (pH 12 to 13.5). Employees must be trained in the proper use and handling of the retarder materials. Minimum recommended PPE is:
Consult the material and equipment manufacturer’s current recommended safety procedure. Consult ICRI Guideline No. 120.1 (Sections 2.0 through 7.0) for guidelines and recommendations for safety in the concrete repair industry. Refer to Appendix C for additional information on safety issues related to concrete surface preparation.
The Method Selection Process
Surface preparation decisions require a thorough understanding of the substrate conditions, protective system or repair material requirements, and job-site conditions. The type of material selected for installation will generally determine the type of surface preparation required and the resulting concrete surface profile (CSP) to be achieved. However, substrate conditions can vary, ranging from concrete in good condition to deteriorated concrete. Careful examination and testing of the substrate will ensure that the proper surface preparation method(s) is/are selected.
The checklists that follow will help ensure that critical information is identified and considered. The information collected during the initial evaluation phase is used to develop criteria for the selection of a surface preparation method(s). Once the criteria have been determined, the Method Selector (Section 7.0) and Method Summaries (Section 8.0) may be used to identify the method, or combination of methods, most likely to produce the desired results for the project.
Substrate Condition
The condition of the substrate, including strength, cause and extent of deterioration, existing coatings and sealers, and many other factors, will define the nature and degree of preparation required. Although a discussion of the various techniques to perform a complete survey of existing conditions is beyond the scope of this guideline, the following checklist provides examples of the types of information that should be considered. Methods to test and verify the surface preparation are provided in Appendix B.
The following is a checklist of the items found in the Substrate Condition Evaluation Tree (Fig. A.1):
Surface Conditions
Efflorescence, Encrustations, Soil
a) Type
b) Thickness
c) Bond strength
Surface Imperfections
a) Laitance
b) Bugholes
c) Dusting
d) Ridges
e) Exposed aggregate
f) Abrasion
Previous Patches
Bond Breaking Contaminants
a) Form Release
b) Curing Compound
c) Existing Membrane/Coatings
d) Oil
e) Latex modifiers
Soundness
Delaminated Concrete Depth
a) Spalled
b) Strength
c) Porosity
d) Freeze/Thaw
e) Alkali Reactivity
f) Sulfate Attack
Pull-off tests
Chloride Content and Penetration Depth
Carbonation Depth and pH
Hazardous Materials
• PCB
• Frangible Asbestos
• Chemicals
• Lead
• Heavy Metals
Finish
Moisture
• Concrete Maturity (Fresh/Green Concrete)
• Hydrostatic Pressure
a) Positive Hydrostatic
b) Negative Hydrostatic
• Substrate Moisture
a) Internal Relative Humidity (Probes)
b) Moisture Vapor Emission
• Vapor Barrier Present
a) Over Granular Fill
b) Under Granular Fill
• No Vapor Barrier
• Drainage
Joints and Cracking
General Observations
Protective system and repair material requirements
Decisions concerning surface preparation cannot be made without knowing the properties and application requirements of the material to be applied. Surface preparation and profile requirements in particular will vary with the repair material and/or protective system.
The following is a checklist of the items found in the Material Requirement Evaluation Tree (Fig. A.2):
Substrate Strength
Tensile bond strength
Profile
• Sealers—0 to 3 mils (0 to 0.075 mm):
CSP 1-2
• Thin film coatings—4 to 10 mils (0.01 to 0.025 mm): CSP 1-3
• High build coatings—10 to 40 mils (0.025 to 1.0 mm): CSP 3-5
• Self-leveling—50 mils to 1/8 in. (1.2 to 3.0 mm): CSP 4-6
• Polymer overlays (1/8 to 1/4 in. ([3 to 6 mm]): CSP 5-9
• Concrete overlays, toppings, and repairs— >1/4 in. (>6 mm): CSP 5-10
Other
Application thickness
Moisture tolerance
a) Wet substrate OK
b) Dry substrate needed
c) Moisture vapor emission
d) Cleaning method
Alkali tolerance
Cleanliness (dust)
Job-site Conditions
Noise, vibration, dust, and water may be generated by various preparation methods. These can disrupt use of the structure or damage its contents. The owner’s need for uninterrupted use of the structure, concerns about the operating environment, or property damage potential may limit the choice of surface preparation method. The generation of dust, slurries, or large volumes of water may introduce requirements for their containment and safe disposal. The type and capacity of mechanical ventilation and available power sources, the size of door openings, and minimum vertical clearance are all examples of application conditions that will affect decisions regarding surface preparation method selection.
The following is a checklist of the items
found in the Jobsite Conditions Evaluation Tree
(Fig. A.3):
Accessibility
• Physical Constraints
a) Height
b) Load Bearing Capacity
c) Doors
d) Access
e) Width/Turning Radius
f) Area
• Surface Orientation
a) Horizontal
b) Vertical
c) Overhead
d) Slab on Grade
e) Supported
• Time
a) Duration
b) Working Hours
c) Complete Closure
d) Available Space
• Obstacles
a) Penetrations
b) Non-Movable Equipment
c) Transitions
d) Elevation
e) Dissimilar Substrates
f) Joints
g) Traffic Requirement
h) Complete Shut-Down
i) Vehicle Access
j) Pedestrian Access
• Exposure
a) Interior
b) Exterior
Environmental Considerations
• Recycling/Disposal
• Airborne (i.e. abrasive blasting)
• Liquid (i.e. hydrodemolition water)
• Solid (i.e. steel shot)
• Debris (i.e. concrete, resteel)
• Hazardous Waste (i.e. existing coating)
• Containment
a) Airborne Debris
b) Liquid/Slurry
c) Drainage—restrictions on use
d) Pre-treatment
e) Noise
f) Vibration
g) Fumes, Exhaust, Solvents
h) Surrounding Area
i) Ventilation—natural or mechanical—
capacity
• Temperature Conditions
• Freezing
• Ambient
• Differential
• Surface
• Variability
• Extreme Heat
Mechanical Data— Utility Supply (type, availability, access location and cost)
• Electricity
a) Volts
b) Phase
c) Amps
d) Locations
e) Cost
• Compressed Air
a) Maximum Pressure
b) CFM Available
c) Locations
d) Cost
• Ventilation
a) Natural
b) Mechanical
1. Capacity (cfm/cmm)
2. Locations
3. Existing HVAC—usable
4. Supply equipment—fans
• Water
a) Portable
b) Volume
c) Pressure
d) Supply pipe diameter
e) On/off valves
f) Location
g) Cost
h) Hot Water
i) Drainage
1. Sanitary Sewer
2. Location
3. Cost
4. Discharge Requirements
5. Permit required
6. Treatment
j) Storm Drain
k) Combined Storm/Sanitary
l) Natural Drainage
m) Pumps Required
n) Sump Pumps/Pits
• Sanitary facilities
a) Restrooms
b) Wash Area
c) Change Area
d) Lighting
e) Type
f) Adequate—more needed
• Fuel
a) Diesel
b) Gasoline
c) LPG Natural
Testing
Test methods to determine the quality and suitability of the concrete surface following surface preparation.
Tensile Bond Strength Test
ICRI Technical Guideline No. 210.3, “Guide for Using In-Situ Tensile Pull-Off Tests to Evaluate Bond of Concrete Surface Materials,” and ASTM C1583/C1583M, “Standard Test Method for Tensile Strength of Concrete Surfaces and the Bond Strength or Tensile Strength of Concrete Repair and Overlay Materials by Direct Tension (Pull-off Method).”
The tensile bond test is used to assess the adequacy of the prepared substrate prior to the installation of material (test the substrate only) or following the application (test the repair composite system). The advantage of evaluating the prepared substrate is that additional surface preparation may be performed if necessary without the cost of removing the applied material afterward. The test is used to determine the potential for bond failure between the applied material and the prepared substrate.
This test is conducted by coring the substrate or repair composite, attaching a metal disc within the cored area, and applying a load perpendicular to the surface and measuring the force required to cause failure at the substrate or within the repair composite. Load at failure is recorded in pounds per square inch (psi). The location of the failure will identify the weakest link in the repair application and may be an indicator of inadequate surface preparation. Tensile bond test devices are shown in Fig. B.1.a and B.1.b.
Adhesion Test
ASTM D7234, “Standard Test Method for Pull-Off Adhesion Strength of Coatings on Concrete Using Portable Pull-Off Adhesion Testers” (Fig. B.2).
This test method covers procedures for evaluating the pulloff adhesion strength of a coating on concrete. The test determines the greatest perpendicular force (in tension) that a surface area can bear before a plug of material is detached.
Failure will occur along the weakest plane within the system, which includes:
• Adhesive to test fixture;
• Adhesive to the coating surface;
• Adhesion of each coating layer within
a system;
• Adhesion of the coating to the substrate; and
• Tensile strength within the substrate.
The general pulloff adhesion test is performed by scoring through the coating down to the surface of the concrete substrate at a diameter equal to the diameter of the loading fixture (dolly, stud), and securing the loading fixture normal (perpendicular) to the surface of the coating with an adhesive. After the adhesive is cured, a testing apparatus is attached to the loading fixture and aligned to apply tension normal to the test surface. The force applied to the loading fixture is then increased and monitored until a plug of material is detached. When a plug of material is detached, the exposed surface represents the plane of limiting strength within the system. The nature of the failure is qualified in accordance with the percent of adhesive and cohesive failures, and the actual interfaces and layers involved. The pulloff adhesion strength is computed based on the maximum indicated load and the fracture surface area.
Knife Adhesion Test
ASTM D6677, “Standard Test Method for Evaluating Adhesion by Knife”
This test method covers the procedure for assessing the adhesion of coating films to the substrate by using a knife. This test method is used to establish whether the adhesion of a coating to a substrate or to another coating (in multi-coat systems) is at a generally adequate level. This test requires uses a utility knife to remove the coating. It helps determine if the adhesion of a coating to a substrate or to another coating (in multi-coat systems) is acceptable.
Using a knife and straightedge, two cuts are made into the coating with a 30- to 45-degree angle between them and down to the substrate, which intersects to form an “X.” At the intersection of the two cuts, the point of the knife is used to attempt to peel the coating from the substrate or from the coating below. This is a highly subjective test and its value depends on the inspector’s experience.
Measuring the Surface pH following Chemical Cleaning
ASTM D4262, “Standard Test Method for pH of Chemically Cleaned or Etched Concrete Surfaces”
Chemical cleaning and etching is sometimes used to prepare concrete for coating. Residual chemicals not removed by water rinsing may adversely affect the performance and adhesion of coatings applied over prepared concrete surfaces. This test method is used to determine if residual chemicals have been removed by measuring the acidity or alkalinity of the final rinsed surface.
Surface Profile
ICRI 310.2R Concrete Surface Profile (CSP) profiles.
The surface preparation specification may include a CSP required profile, which can be compared with the CSP molded replicas available from ICRI. These replicas provide a visual comparison with the actual profile created during the surface preparation.
Place CSP replicas (Fig. B.3) on the prepared surface and visually compare the profile with the replicas. The profile of the surface should be in the range specified.
Measuring the Surface Profile
Visual observation of the surface profile may not provide a satisfactory determination of the surface profile. More qualitative/quantitative methods, including the Replica Putty and Sand Method, are available to further define the surface profile. The measurement of roughness can lead to optimization of bonding strength.
Replica Putty
ASTM D7682, “Standard Test Method for Replication and Measurement of Concrete Surface Profiles Using Replica Putty”.
Ensuring that the correct surface profile has been achieved can best be done with the use of replica putty. A permanent replication of the surface may be viewed (Method A—Fig. B.4.a) and/or measured (Method B—Fig. B.4.c) to form a permanent record of the surface preparation.
Replica putty is applied to the surface (Fig. B.4.b) and allowed to cure. Once removed from the surface, the putty represents a reverse image of the surface. The peaks and valleys of the surface can be measured using a specially modified thickness gauge (Fig. B.4.c). The data can be analyzed to determine the surface profile range (highest measured peak to lowest measured valley).
Replica Tape
ASTM D4417, “Standard Test Methods for Field Measurement of Surface Profile of Blast Cleaned Steel”
Method C uses a special tape containing compressible foam attached to a noncompressible uniform plastic film (Fig. B.5.a and B.5.b). A burnishing tool is used to impress the foam face of the tape into the surface to create a reverse replica of the profile that is measured using a spring-loaded micrometer. This method is designed for relatively smooth surfaces (CSP 1 to 3) prepared using sand, grit abrasive blasting, or steel shotblasting and may not be applicable to rougher profiles.
Laser Profilometry
The digital surface roughness meter (DSRM) measures the surface roughness of a prepared surface using a line laser.
The DSRM (Fig. B.6) is placed flush with the surface to be measured. An image of the profile is transmitted to a computer, where the image is digitized; the profiles are automatically isolated and measured for roughness. This method will provide a permanent record of the surface roughness. (Maerz, N. H.; Chepur, P.; Myers, J.; and Linz, J., 2001, “Concrete Roughness Measurement Using Laser Profilometry for Fiber Reinforced Polymer Sheet Application,” Presented at the Transportation Research Board 80th Annual Meeting, 12 pp.)
Sand Method
ASTM E965, “Standard Test Method for Measuring Pavement Macrotexture Depth Using a Volumetric Technique”
The average surface texture (macro-texture) may be measured using a known volume of sand or other fine grain material and spreading it uniformly over the surface and measuring the area covered. Using the standard formula for volume (L × W × D), the approximate amplitude of the surface may be determined. This method will assist in determining the amount of material that may be necessary to fill the macro-texture before applying a uniform layer of material over the surface.
Apply a known volume of sand to the surface. Carefully spread the sand in a circular motion using a large flat spreading tool, slowly increasing the diameter of the circular motion until all the sand has been spread. Measure the diameter of the circle and calculate the average depth. AD = (V sand/A area of the circle). Figures B.7.a and B.7.b depict this method.
Visual Inspection
ASTM D4258, “Standard Practice for Surface Cleaning Concrete for Coating”
This describes a method of surface cleaning that is intended to provide a clean, contamination- free surface without removing concrete from an intact, sound surface. Following the cleaning, visually examine the prepared surface to verify that it is free of debris, dust, dirt, oil, grease, loosely adherent concrete, and other contaminants. Test surfaces cleaned with detergent or non-solvent emulsifying agents for pH following ASTM Test Method D4262. Moisture content may be determined following ASTM Test Method D4263.
Petrographic Analysis
ASTM C856, “Standard Practice for Petrographic Examination of Hardened Concrete”
While petrography can be used to detect a variety of flaws within concrete, it can also be used following surface preparation to determine if the method used to prepare the surface caused microcracking in the substrate.
The test is made by extracting a sample of the concrete and observing it under a microscope (Fig. B.8.a). Microcracks (Fig. B.8.b) weaken the substrate and should be removed by further surface preparation prior to installation of any materials.
Surface Cleanliness Fig. B.10.a: Electromechanical sounding device Using Tape
ASTM E1216, “Standard Practice for Sampling for Particulate Contamination by Tape Lift”
This practice covers procedures for sampling surfaces to determine the presence of particulate contamination 5 mm and larger. The practice consists of the application of a pressure-sensitive tape to the surface followed by the removal of particulate contamination with the removal of the tape (Fig. B.9).
Sounding the Surface
ASTM D4580/D4580M, “Standard Practice for Measuring Delaminations in Concrete Bridge Decks by Sounding”
The surface may be sounded either before or after surface preparation to determine if there is any delaminated concrete. Delaminated concrete will produce a hollow sound when a chain is dragged over the area or the surface is struck with a hammer. Areas that are delaminated should be marked for further preparation.
Water Absorption
ASTM F21, “Standard Test Method for Hydrophobic Surface Films by the Atomizer Test”
The presence of water-repelling materials may interfere with the bond or penetration of applied material. Surface preparation should remove any water-repellent material that may interfere with the performance of the applied material. The atomizer test is performed by applying a fine water spray to the dry concrete surface and observing the wetting pattern. In the absence of hydrophobic films, the water droplets will wet the surface and spread immediately and darken the surface as the water is absorbed. In areas where hydrophobic materials are present on the surface, the water will not wet the surface but will tend to remain as fine droplets or beads of water on the surface (Fig. B.11). This test is less effective on extremely low-permeability concrete or surfaces with dense finishes upon which water may bead, even in the absence of hydrophobic materials.
Moisture in Concrete
High levels of moisture in a concrete substrate can have a detrimental effect on many types of applied materials. Most manufacturers of coatings and overlay materials have specific levels of moisture that must be reached before their products can safely be installed. ASTM offers several methods to measure moisture in concrete slabs, as follows:
1. Prepare a 20 x 20 in. (500 x 500 mm) area of the concrete surface by dry vacuum grinding to a CSP 1 to 2 to remove any existing coatings, adhesive, or surface contamination. Note: If an existing coating, sealer, or adhesive is removed, the prepared surface must be left open for 24 hours before installing the test kit. If the surface was bare concrete, then after the surface is ground, the kit can be installed immediately.
2. The dish of calcium chloride crystals with lid and tape is weighed to the nearest 0.004 oz (0.1 g) on a calibrated gram scale.
3. The starting weight, date, time, location, and ambient conditions are recorded along with the name of the person performing the test.
4. The tape is removed and taped to the underside of the plastic dome, the dish is opened, and the lid is inverted and placed beneath the dish and placed in the center of the prepared area.
5. Immediately after setting the dish, the plastic dome is placed over the dish with the dish as close to the center beneath the dome as possible, and the dome is sealed to the concrete surface.
6. After a minimum of 60 hours, but no more than 72 hours, the dish is removed and resealed with the original lid and tape.
7. The sealed dish is reweighed on a calibrated scale.
8. The moisture vapor emission rate (MVER) is calculated by multiplying the increase in weight by the exposure area and dividing by the time period. The MVER value is expressed in pounds of water / 1000 ft2 (100 m2) / 24 hours.
This test method measures the moisture within the concrete and is a predictor of what the moisture level will be in the slab, top-to bottom, once the slab is covered. The method uses a humidity probe (Fig. B.12.c) to measure the relative humidity in a concrete subfloor at a specific target depth. For slabs on ground or on a metal deck, the measurement is taken at a depth equaling 40% of the slab thickness. If the slab is elevated such that it can dry from the top and bottom, the measurement is taken at 20% of the slab thickness. A rotary hammer drill with a carbide bit is used to drill into the concrete to the target depth. After the proper depth has been confirmed, the hole is brushed and vacuumed thoroughly clean. A full-depth ribbed hole liner is then inserted to the bottom of the drilled hole such that a relative humidity (RH) measurement can be taken at the specific target depth after the liner has been in place for a minimum period of 72 hours. The RH probe (Fig. B.12.d) can be installed immediately and left in place for the entire test period or inserted after the 72-hour equilibration period. A measurement is recorded on the reader unit when the RH % does not drift more than 1% in 5 minutes which, in most cases, will take at least 1 hour after a probe is inserted into the liner.
The hood method (Fig. B.12.e) is similar to the ASTM F1869 calcium chloride method. However, the units are different and therefore not directly comparable as the hood method is measuring the RH above the slab, while the calcium chloride test is measuring pounds of moisture vapor emission per 1000 ft2 (100 m2) per 24-hour period. Both of these tests measure moisture in approximately the top 1/4 to 1/2 in. (6 to 13 mm) of the slab while ASTM F2170 measures moisture within the slab thickness. The hood test is performed by:
1. Cleaning the surface;
2. Sealing an insulated hood firmly to the concrete substrate;
3. Placing a stopper in the probe hole;
4. Allowing a minimum period of 72 hours to elapse before taking readings with a probe;
5. Removing the stopper;
6. Inserting a humidity probe and allowing the probe to equilibrate (probe has reached equilibrium when RH readings do not drift more than 1% over a period of 20 minutes); and
7. Taking readings using the humidity probe (Fig. B.12.e).
ICRI Concrete Slab Moisture Testing Certification Program
ICRI has a Concrete Slab Moisture Testing Certification program. The purpose of this program is to help improve the performance of concrete slab moisture testing in the United States to result in more consistent, accurate results that will help flooring manufacturers, architects, and contractors to make better decisions as to when a concrete floor is ready for a floor-covering installation. This certification program has two tiers and the certification is valid for 5 years. Tier 1 applicants are those who are not regularly engaged in moisture testing, yet have an active interest in learning more about the tests, what the tests mean, and how the tests should be performed. Tier 2 applicants are those who have applied for full certification as an ICRI Concrete Slab Moisture Testing Technician—Grade 1. The ICRI certification program is based on the following four (4) ASTM Standards, including all Annexes and Appendixes:
Safety recommendations for each method are included in the Safety section of the method summaries. This information is intended only to alert users to the nature of the safety issues associated with the method described. Consult the equipment manufacturer’s safety requirements for each type of equipment described.